With inflation always looming, the news at Rio Rancho city council’s meeting on Wednesday was a pleasant surprise.
That’s because the bid to deliver water to the new Sue Cleveland High School came in 20 percent below the engineer’s estimate.
|
|
Rio Rancho Public Works Director Lisa Vornholt informed the councilors that the contract is for $2,153,892.88. The original estimate was $2,680,415
“What happens in a market like this is certainly material costs have gone up but when contractor’s don’t have that many jobs going on, we get a lot of bids,” Vornholt said.
Vornholt said there were eight other bids. The contract covers a three-month construction period with completion in mid-December.
The water line runs from a location near the city center, east along Paseo del Volcan to the school.
The money for the project is coming from the city’s water capital improvement fund.